P & O Cold Logistics recently employed Clarion
Construction, Inc. to design and manage construction of a new 146,000 s.f.
Distribution Center in Carson, California.
|
|
| |

|
|
| |
Working with Oltman's Construction, the new building was recently
erected and is currently receiving the roof structure.
|
|
| |

|
|
| |

Photo Taken 11-15-01
|
|
| |
The 6" thick insulated wall panels being installed by Clarion crews as manufactured by
Metl-Span Corporation.
|
|
| |

Photo Taken 11-15-01
|
|
| |

Photo Taken 11-23-01
|
|
| |
New Metl-Span panels being installed at the freezer perimeter, ammonia coils hung and lighting in place.
|
|
| |

Photo Taken 05-22-02
|
|
| |
The completed dock sparkles featuring a Kalman Floor
and Metl-Span panels.
|
|
| |

Photo Taken 05-22-02
|
|
| |

Photo Taken 05-22-02
|
|
| |
The Repack Area with all sanitary finishes.
|
|
| |

Photo Taken 05-22-02
|
|
| |
The USDA Inspection Area is "State of the Art".
|
|
| |

Photo Taken 05-22-02
|
|
| |
The freezer space is divided in several rooms which are convertible from freezer to cooler.
|
|
| |

Photo Taken 05-22-02
|
|
| |

Photo Taken 05-22-02
|
|